August 12th  Rearranged the garage to fit the wings

August 13th  Panel update, angle of attack gauge arrives

August 15th  Wings mated!

August 18th  Set incidence, drilled rear spar, started flap install

August 19th  Finished right side flap actuator hole, connected right flap

August 20th  Left side flap actuator tube hole, connected L flap, started connecting ailerons

August 21st  Hooked up right aileron, started to figure out the flap notch arm install

August 22nd  Flap notch arm fitting, drilled tunnel cover for notch arm and doubler

August 23rd  Dimpled and painted tunnel cover/doubler, drilled tank attach angle

August 25th  Finished flaps, started fuel and vent line routing

August 26th  Finished fuel tank vent lines

August 27th  F-721B forward side brace

August 28th  Riveted F-721B's

August 29th  Wing root fairings (no pics)

August 31st  Finished fuel lines, fit F-785A center brace for F-705 bulkhead

 