July 2007 Fuselage

July 1st  Fit and drilled the F-751 and F-652 bulkheads

July 2nd  Drilled holes for platenuts, riveted them in place

July 4th  Made the seatbelt wear blocks

July 5th  Bulkhead cover temporarily installed

July 7th  Baggage tunnel cover, seat hinges, baggage side skins, removed aft top skins

July 8th  Fit F-749L/R side covers, drilled seat hinges to the seat skins

July 9th  Riveted seat hinges to seat pans, riveted seat pans to ribs, started on center tunnel cover

July 10th  Made my own center tunnel cover

July 11th  Remade the center tunnel cover, riveted platenuts

July 12th  Started seatbacks

July 14th  Seatbacks

July 15th  Seatback braces

July 16th  Finished seatback braces, started on forward section covers

July 17th  Forward section covers

July 18th  F-704 fuel line covers, F-7114 gussets

July 20th  Installed F-782D's, F-7114 gussets, and F-796 forward wing attach bracket

July 22nd  Installed flap handle, control column, started on aileron boots

July 30th  Installed aileron boots

 