September 1  Deburred and scotchbrited flap and aileron braces...

September 2  No building, second tech visit, carpeted table...

September 3  Riveted braces, ran pitot lines...

September 4  Finished pitot, hung skins, ran wire...

September 5  Dimpled access holes, riveted platenuts...

September 7  Started riveting left bottom inboard wing skin...

September 9  Finished riveting left bottom inboard skin...

September 10  Riveted left outboard bottom skin...

September 11  Switched wings, riveted access hole platenuts...

September 13  Started riveting right inboard bottom skin...

September 15  More bottom wing walk riveting...

September 22  Bottom wing skin riveting...

September 23  Finished right inboard bottom skin...

 